China audit finds slow progress on Beijing's new airport project

1
2015-12-11 08:35Xinhua Editor: Mo Hong'e

The construction of Beijing's new airport is behind schedule due to lagging land requisition and demolition work, the country's top auditing authority said on Thursday.

By the end of October, Beijing and Hebei province delivered less than half of the total land needed, with 16.7 million out of all 27.3 million square meters of land still required, according to a report from the National Audit Office.

The new airport, which was authorized for construction by the State Council in December 2012 and is considered a key step for the coordinated development of the Beijing-Tianjin-Hebei region, is expected to be finished by 2019.

Meanwhile, the report showed that many other major construction projects were also behind schedule with 12 railway projects barely achieving 10 percent of their annual plans which involve 8.57 billion yuan (1.33 billion U.S. dollars) of planned investment.

 

  

Related news

MorePhoto

Most popular in 24h

MoreTop news

MoreVideo

News
Politics
Business
Society
Culture
Military
Sci-tech
Entertainment
Sports
Odd
Features
Biz
Economy
Travel
Travel News
Travel Types
Events
Food
Hotel
Bar & Club
Architecture
Gallery
Photo
CNS Photo
Video
Video
Learning Chinese
Learn About China
Social Chinese
Business Chinese
Buzz Words
Bilingual
Resources
ECNS Wire
Special Coverage
Infographics
Voices
LINE
Back to top Links | About Us | Jobs | Contact Us | Privacy Policy
Copyright ©1999-2018 Chinanews.com. All rights reserved.
Reproduction in whole or in part without permission is prohibited.