CNOOC's LNG imports.(Photo/China Daily)
Fujian LNG terminal, the country's largest liquefied natural gas project in terms of storage capacity, started building two more storage tanks on Tuesday, a move that will facilitate offshore gas transportation and the pipeline network.
The two tanks, which can hold 160,000 cubic meters of gas each, will be added to the existing LNG station in Putian, Fujian province, the project's operator said in a statement.
China National Offshore Oil Corp said the construction of the two tanks is expected to be completed by 2018.
Fujian LNG terminal consists of a wharf, six storage tanks and pipelines. After completion, it will be able to receive as much as 6.3 million metric tons of LNG per year, CNOOC said.
Yang Hua, chairman of CNOOC, said that the company plans to provide more clean energy especially in the coastal regions during the 13th Five-Year Plan (2016-20).
"We will continue to push the LNG industry as well as related technologies, making our efforts to optimize the country's energy mix," he said.
The global glut and sluggish economy will continue to drive down prices of LNG, which means that imports of the super-cooled fuel is cheaper than domestic production, experts said. They added that China's LNG imports are expected to rise in the long term amid mounting pressure caused by air pollution.
Neil Beveridge, a senior analyst at Bernstein Research, said that China's gas demand is also expected to increase after rising 14 percent in the first quarter.
"Imports of LNG will also accelerate this year, driven by the ramp-up of a number of Australian LNG projects contracted to China," he added.
LNG is natural gas that has been changed into a liquid state by cooling it to minus 162 C, which poses high requirements for technologies and tank structure.
Since 2008, CNOOC has formed a team to develop the LNG storage technology called full containment LNG storage tank. Just a few countries in the world have the ability to produce such facilities.
CNOOC is running the Dapeng LNG terminal in Guangdong, the country's first and largest LNG importer, as well as six other LNG receiving stations in Shanghai, Fujian, Zhejiang, Tianjin and Zhuhai, with a total capacity of 27.8 million tons per year.
Last year, CNOOC imported 1.3 million tons of LNG, accounting for 70 percent of the country's total LNG imports.