2-year test of UHV direct current project completed  

世界首个特高压直流输电工程完成孤岛运行调试

中国南方电网公司31日宣布,世界第一个±800千伏直流输电工程——云南-广东特高压直流输电工程(简称“云广工程”),孤岛运行调试500万千瓦试验取得成功。

2013-04-01 13:12 Ecns.cn     Web Editor: qindexing comment

Guangzhou (CNS) -- Testing has been completed on an 800-kilovolt direct current transmission (DCT) project in south China's Yunnan and Guangdong provinces, the China Southern Power Grid said on Sunday.

The Yunnan-Guangdong ultra-high voltage DCT project tested a transmission capacity of five million kilowatts.

Six phases of a capacity test ranging from one million to five million kilowatts of direct current have been carried out in the past two and a half years, according to the company.

Direct current transmission is an "island transmission system" that is independent from the nationwide power grid. The isolated system will supplement the transmission of the grid, while avoiding break downs when the grid does.

Comments (0)

世界首个特高压直流输电工程完成孤岛运行调试

中国南方电网公司31日宣布,世界第一个±800千伏直流输电工程——云南-广东特高压直流输电工程(简称“云广工程”),孤岛运行调试500万千瓦试验取得成功。

>>详细

Copyright ©1999-2011 Chinanews.com. All rights reserved.
Reproduction in whole or in part without permission is prohibited.