Main electrical network in quake-hit Lushan repaired   

四川芦山震区电网全部实现主网供电

“4•20”四川芦山震区截至13日已完成电网恢复阶段各项任务,灾区全部实现主网供电,电网供电能力基本恢复到震前水平。目前,抗震救灾工作已转入灾后重建阶段,预计“十二五”末将全面完成。

2013-05-14 13:09 Ecns.cn     Web Editor: Wang YuXia comment

Beijing (CNS) - The main electric power supply network of the quake-affected areas in Lushan of Sichuan province resumed operation on May 13, the State Grid Corporation of China (SGCC) said Monday. The power supply capacity has been returned to the level before the earthquake.

A total of 186,600 local households that suffered from power outages now have electricity or have access to power supply.

The 34 disaster-affected transformer substations with 35 kv and above resumed operation and 263 of the 265 wires with 10 kv and above have also been restored power, according to the SGCC.

In addition, with the restoration of the last four 35–kv substations, the four-level communication network has fully recovered in Ya'an.

The SGCC Sichuan branch has been making plans for post-quake reconstruction and is striving to complete grid transmission and distribution facilities by April 20, 2014.

Before the end of 2015, it also plans to complete grid-improvement projects in the disaster areas.

Comments (0)

四川芦山震区电网全部实现主网供电

“4•20”四川芦山震区截至13日已完成电网恢复阶段各项任务,灾区全部实现主网供电,电网供电能力基本恢复到震前水平。目前,抗震救灾工作已转入灾后重建阶段,预计“十二五”末将全面完成。

>>详细

Copyright ©1999-2011 Chinanews.com. All rights reserved.
Reproduction in whole or in part without permission is prohibited.